Purpose
To provide requirements for the contents of a slope stability report to justify installation of a septic system on slopes over 30 percent or in potentially unstable slopes.
Slope Stability Report Requirements
Slope stability reports shall be prepared by either a civil engineer or a geotechnical engineer registered in the state of California.
Slope Stability Reports shall include the following applicable items:
- Cover Sheet
- Name of Project
- Site Address(es)
- Assessor’s Parcel Number(s)
- Preparer’s name and contact information
- Seal and signature of licensed civil engineer or geotechnical engineer
- Date Prepared
- General Project Information
- Project description and scope of evaluation
- Description of proposed onsite wastewater treatment system (OWTS) type
- Site Reconnaissance
- Description of slope geometry and topography including topographic maps and aerial imagery for steep slopes, ravines, or previous landslides
- Description of soils and geologic maps identifying weak, clay-rich, or loose alluvial soils
- Identification of observed groundwater levels or mottling during site evaluations and proximity to seeps, springs, or streams. Including wet areas that may indicate perched water tables
- Evidence of instability (example, sloughing, cracking, creep, landslide scars, bending trees)
- Proposed onsite wastewater treatment system (OWTS) location relative to slopes
- Photographs of the site slopes
- Geologic Evaluation Analysis
- Methodologies used for evaluation (example, visual observation, slope stability analysis methods, software)
- Discussion of the presence of groundwater and seasonal variations thereof
- Impacts of anticipated effluent loading
- Factor of Safety analysis for the site under saturated conditions.
- Downslope Hazard / Risk Assessment
- Identify the types of hazards (landslide, effluent breakout, etc.)
- Identify potential sources of harm (existing structures, roadways, human or animal exposure, streams, rivers, and natural resources)
- Analyze the probability of each hazard
- Analyze the severity of potential harm
- Identify and implement control measures to eliminate or reduce the risks
- Mitigations and Recommendations for installation of proposed onsite wastewater treatment system (OWTS)
- Siting and layout
Examples may include but are not limited to:- Place septic tanks and leach fields away from steep or unstable slopes
- Maintain regulatory setbacks from slope crests, toes, and drainage channels
- Avoid placing systems on fill or loose alluvium
- Drainage control.
Examples may include but are not limited to:- Divert surface water away from septic areas
- Install perimeter swales or interceptor drains to reduce slope saturation
- Avoid leakage from system components; monitor and maintain pipes and tanks
- Slope reinforcement (as applicable).
Examples may include but are not limited to:- Consider terracing or benches to reduce slope angle in critical areas
- Retaining walls or soil nails may be used to fill or structures are needed
- Ensure septic system footprint is not compromised by slope reinforcement
- Soil improvement (as applicable).
Examples may include but are not limited to:- Use engineered fill where appropriate, with proper compaction
- Avoid excessive disturbance of native soils during construction
- System design adaptations (as applicable).
Examples may include but are not limited to:- Pressure-dosed or drip distribution can reduce infiltration on slopes
- Lined trenches may prevent percolation into marginal soils
- Design for long-term monitoring and maintenance to prevent saturation or slope weakening
- Siting and layout
- Conclusion
- Summary of stability issues addressed
- Professional statement confirming site suitability